School Renewal Investment Reports
Capital Projects for 2024-2025
Update for Progress/Completion
| School | Description | Start Date | Completion Date | Percent Complete |
| Lockerby C.S. | Ventilation, interior work | 01-Oct-24 | 01-Mar-26 | 95% |
| Lively District S.S. | Site work, exterior work | 02-Jul-25 | 31-Oct-25 | 100% |
| Levack P.S. | Roof, site work | Deferred | N/A | N/A |
| Copper Cliff P.S. | Roof, site work, exterior work | 02-Jul-25 | 31-Oct-25 | 100% |
| Espanola H.S. | Electrical, site work | 02-Jul-25 | 01-Mar-26 | 90% |
| Lo-Ellen Park S.S. | Mechanical, exterior work | 02-Jul-25 | 31-Oct-25 | 100% |
| Monetville P.S. | Roof, site work | 02-Jul-25 | 30-Apr-26 | 80% |
| Northeastern E.S. | Site work | 02-Jul-25 | 31-Oct-25 | 100% |
| Assiginack P.S. | Heating | 02-Jul-25 | 31-Oct-25 | 100% |
| Chelmsford Valley District C.S. | Site work | 01-Aug-25 | 31-Oct-25 | 100% |
| Walden P.S. | Site work, solar panels | 02-Jul-25 | 31-Oct-26 | 50% |
| Centre for Education | Ventilation | 01-Sep-25 | 30-Nov-25 | 100% |
| Lancer Dome | Storage | 01-May-25 | 31-Oct-25 | 100% |
| Little Current P.S. | Lockdown system | Deferred | N/A | N/A |
Planned Projects for 2025-2026
| School | Description | Start Date | Completion Date | Percent Complete |
| R.L. Beattie P.S. | Lockdown system | 30-Jun-26 | 30-Aug-26 | 0% |
| Copper Cliff P.S. | Interior work | 30-Jun-26 | 15-Oct-26 | 0% |
| C.R. Judd P.S. | Site work | 30-Jun-26 | 01-Nov-26 | 0% |
| Lansdowne P.S. | Interior work | 30-Jun-26 | 15-Nov-26 | 0% |
| R.H. Murray P.S. | Site work | TBD | TBD | |
| Northeastern E.S. | Electrical | 31-Jan-26 | 28-Feb-26 | 65% |
| Westmount P.S. | Ventilation | 16-Mar-26 | 31-Jul-26 | 0% |
| S. Geiger P.S. | Roof work | 30-Jun-26 | 01-Aug-26 | 0% |
| Little Current P.S. | Lockdown system | 30-Jun-26 | 30-Aug-26 | 0% |
| Central Manitoulin P.S. | Interior work | 29-Jun-26 | 28-Aug-26 | 0% |
| Confederation S.S. | Interior/site work | 29-Jun-26 | 28-Aug-26 | 0% |
| Lasalle S.S. | Interior/roof work | 16-Mar-26 | 15-Oct-26 | 0% |
| Lockerby C.S. | Ventilation/structural | 29-Jun-26 | 15-Oct-26 | 0% |
| Sudbury S.S. | Structural/drainage | 29-Jun-26 | 31-Aug-26 | 0% |
| Espanola H.S. | Ventilation | 29-Jun-26 | 15-Oct-26 | 0% |
| Manitoulin S.S | Heating | 06-Jul-26 | 15-Oct-26 | 0% |
| Levack P.S. | Interior/site work | TBD | TBD | |
| Walden P.S. | Solar panels | 02-Jul-25 | 31-Oct-26 | 0% |
| Lively D.S.S. | Exterior work | 29-Jun-26 | 28-Aug-26 | 0% |